Red Bull is carried out as a $ 1.7B plant after delay.

This audio is automatically created. Please let me know if there is feedback.

Red Bull began with a four -year delay in a $ 1.7 billion new facility in Concordes, North Carolina.

This facility is Red Bull, Packaging Supplier Ball Corp. And co -manufacturing and distribution centers of Rauch Fruchtsäfte, Austrian beverage company. According to Red Bull, the company is the second manufacturing plant of the US company and to meet the local market demand.

The spokesman said that the 23.6 million square feet of facilities are expected to start operating in 2028 and reach the maximum capacity by 2031. It will fill up to 3 billion cans every year and it is expected to create 700 jobs.

There was a project It was first announced in 2021Construction began on September 9th. The spokesman did not specify the reason for the delay.

Red Bull, Ball and Rauch Fruchtsäfte opened the first US factory in the United States. Arizona Glen Dale in 2021. The North Carolina site is to make up for Arizona’s position by manufacturing Red Bull Energy Drinks for the United States, but “we need the ability to manufacture for other markets,” the spokesman said.

no way 50% tariff of aluminum This year, the Trump administration has pushed more beverage packaging in the United States.

Headquartered in Austria, RED BULL is building a North Carolina facility as the Global Energy Drink Market grows. $ 12.5 billion by 2030.

Founded in the 1980s, Red Bull is one of the pioneers in the energy category. Competition is intensifying as more new companies join the field and beverage companies expand their energy products. Neat doctor,,, Pepsikoand Anheuser-Busch Invest in all spaces.